A can do a piece of work in 6 days and B can do it in 8 days. How long will they take to complete it together?
Answer
Given:
A can do the work in 6 days ⇒ A's 1 day's work = 61
B can do the work in 8 days ⇒ B's 1 day's work = 81
(A + B)'s 1 day's work
=61+81 L.C.M. of 6 and 8 = 24 =244+243=244+3=247
Time taken by both together = 724=373 days
Hence, A and B together will complete the work in 373 days.
A and B working together can do a piece of work in 10 days. B alone can do the same work in 15 days. How long will A alone take to do the same work?
Answer
Given:
(A + B)'s 1 day's work = 101
B's 1 day's work = 151
A's 1 day's work
=101−151 L.C.M. of 10 and 15 = 30 =303−302=303−2=301
Time taken by A alone = 30 days
Hence, A alone will take 30 days to do the work.
A can do a piece of work in 4 days and B can do the same work in 5 days. Find, how much work can be done by them working together in: (i) one day (ii) 2 days.
What part of work will be left, after they have worked together for 2 days?
Answer
Given:
A's 1 day's work = 41
B's 1 day's work = 51
(i) (A + B)'s 1 day's work
=41+51 L.C.M. of 4 and 5 = 20 =205+204=205+4=209
Hence, in one day they can do 209 of the work.
(ii) Work done in 2 days
=2×209=2018=109
Hence, in 2 days they can do 109 of the work.
Work left after 2 days
=1−109=1010−9=101
Hence, 101 of the work will be left.
A and B take 6 hours and 9 hours respectively to complete a work. A works for 1 hour and then B works for two hours.
(i) How much work is done in these 3 hours?
(ii) How much work is still left?
Answer
Given:
A's 1 hour's work = 61
B's 1 hour's work = 91
(i) Work done by A in 1 hour = 61
Work done by B in 2 hours = 2×91=92
Total work done in these 3 hours
=61+92 L.C.M. of 6 and 9 = 18 =183+184=183+4=187
Hence, 187 of the work is done in these 3 hours.
(ii) Work still left
=1−187=1818−7=1811
Hence, 1811 of the work is still left.
A, B and C can do a piece of work in 12, 15 and 20 days respectively. How long will they take to do it working together?
Answer
Given:
A's 1 day's work = 121
B's 1 day's work = 151
C's 1 day's work = 201
(A + B + C)'s 1 day's work
=121+151+201 L.C.M. of 12, 15 and 20 = 60 =605+604+603=605+4+3=6012=51
Time taken by all together = 5 days
Hence, A, B and C together will take 5 days to complete the work.
Two taps can fill a cistern in 10 hours and 8 hours respectively. A third tap can empty it in 15 hours. How long will it take to fill the empty cistern, if all of them are opened together?
Answer
Given:
First tap fills in 10 hours ⇒ 1 hour's work = 101
Second tap fills in 8 hours ⇒ 1 hour's work = 81
Third tap empties in 15 hours ⇒ 1 hour's work = −151 (emptying)
Work done in 1 hour when all are opened together:
=101+81−151 L.C.M. of 10, 8 and 15 = 120 =12012+12015−1208=12012+15−8=12019
Time taken to fill the cistern = 19120=6196 hours
Hence, the cistern will be filled in 6196 hours.
Mohit can complete a work in 50 days, whereas Anuj can complete the same work in 40 days.
Find:
(i) work done by Mohit in 20 days.
(ii) work left after Mohit has worked on it for 20 days.
(iii) time taken by Anuj to complete the remaining work.
Answer
Given:
Mohit's 1 day's work = 501
Anuj's 1 day's work = 401
(i) Work done by Mohit in 20 days
=20×501=5020=52
Hence, Mohit does 52 of the work in 20 days.
(ii) Work left
=1−52=55−2=53
Hence, 53 of the work is left.
(iii) Time taken by Anuj to do 53 of the work
=53÷401=53×40=24 days
Hence, Anuj will take 24 days to complete the remaining work.
Joseph and Peter can complete a work in 20 hours and 25 hours respectively.
Find:
(i) work done by both together in 4 hrs.
(ii) work left after both worked together for 4 hrs.
(iii) time taken by Peter to complete the remaining work.
Answer
Given:
Joseph's 1 hour's work = 201
Peter's 1 hour's work = 251
(Joseph + Peter)'s 1 hour's work
=201+251 L.C.M. of 20 and 25 = 100 =1005+1004=1005+4=1009
The total work done by Joseph and Peter in 1 hour = 1009.
(i) Work done by both in 4 hours
=4×1009=10036=259
Hence, both together do 259 of the work in 4 hours.
(ii) Work left
=1−259=2525−9=2516
Hence, 2516 of the work is left.
(iii) Time taken by Peter to do 2516 of the work
=2516÷251=2516×25=16 hours
Hence, Peter will take 16 hours to complete the remaining work.
A is able to complete 31 of a certain work in 10 hrs and B is able to complete 52 of the same work in 12 hrs.
Find:
(i) how much work can A do in 1 hour?
(ii) how much work can B do in 1 hour?
(iii) in how much time will the work be completed, if both work together?
Answer
Given:
A completes 31 of the work in 10 hours.
B completes 52 of the work in 12 hours.
(i) A's 1 hour's work
=31÷10=31×101=301
Hence, A can do 301 of the work in 1 hour.
(ii) B's 1 hour's work
=52÷12=52×121=602=301
Hence, B can do 301 of the work in 1 hour.
(iii) (A + B)'s 1 hour's work
=301+301=301+1=302=151
Time taken to complete the work together = 15 hours
Hence, working together they will complete the work in 15 hours.
Shaheed can prepare one wooden chair in 3 days and Shaif can prepare the same chair in 4 days. If they work together, in how many days will they prepare:
(i) one chair?
(ii) 14 chairs of the same kind?
Answer
Given:
Shaheed's 1 day's work = 31
Shaif's 1 day's work = 41
(Shaheed + Shaif)'s 1 day's work
=31+41 L.C.M. of 3 and 4 = 12 =124+123=124+3=127
The total work done by Shaheed and Shaif in 1 day = 127
(i) Time taken to prepare 1 chair = 712=175 days
Hence, working together they will prepare one chair in 175 days.
(ii) Time taken to prepare 14 chairs
=14×712=2×12=24 days
Hence, they will prepare 14 chairs in 24 days.
A, B and C together finish a work in 4 days. If A alone can finish the same work in 8 days and B in 12 days, find how long will C take to finish the work.
Answer
Given:
(A + B + C)'s 1 day's work = 41
A's 1 day's work = 81
B's 1 day's work = 121
C's 1 day's work
=41−81−121 L.C.M. of 4, 8 and 12 = 24 =246−243−242=246−3−2=241
Time taken by C alone = 24 days
Hence, C will take 24 days to finish the work.