Mathematics
A can do a piece of work in 5 days and B can do the same work in (x + 5) days. The total number of days taken by A and B, working together, . The value of x is :
5
10
15
Quadratic Equations
20 Likes
Answer
A can do a piece of work in 5 days.
So, in 1 day
A will do th of the work.
B can do a piece of work in (x + 5) days.
So, in 1 day
B will do of the work.
Work done by A and B in 1 day =
Days taken to complete work =
Hence, Option 1 is the correct option.
Answered By
3 Likes
Related Questions
27 is divided into two parts such that the sum of their reciprocal is . Find the ratio between the numbers (5 : 4).
A and B together can do a piece of work in 6 days. Whereas A alone can do the same work in 9 days. Then B alone will do same work in:
15 days
6 days
18 days
54 days
An article is bought for ₹ x and is sold at the profit of x %. If its selling price is ₹ 56, the cost price is :
₹ 60
₹ 50
₹ 40
₹ 28
An empty tank is filled by a pipe in 2 hours, whereas an another pipe empties the full tank in 3 hours. If the tank is empty and both the pipes are opened together the tank will be filled in:
5 hours
1 hour
6 hours
none of these