A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
Direct & Inverse Variations
6 Likes
Answer
A's 1 day work =
B's 1 day work =
(A + B)'s 1 day work =
=
=
=
(A + B)'s 2 day work =
=
Remaining work =
=
=
No. of days taken by A to finish the remaining work =
=
=
=
Hence, A will take 10 days to finish the remaining work.
Answered By
3 Likes
Related Questions
A can do a piece of work in 24 days, A and B can do it in 16 days and A, B and C in days. In how many days can A and C do it working together?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can do a piece of work in 10 days, B in 18 days, and A, B and C together in 4 days. In what time would C do it alone?
A can do of a work in 5 days and B can do of the same work in 10 days. Find the number of days in which both working together will complete the work.