Mathematics
A and B complete a piece of work in 24 days. B and C do the same work in 36 days, and A, B and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?
Direct & Inverse Variations
12 Likes
Answer
(i) (A + B)'s 1 day work =
(B + C)'s 1 day work =
(A + B + C)'s 1 day work =
A's 1 day work = (A + B + C)'s 1 day work - (B + C)'s 1 day work
=
=
=
Number of days required by A alone = 36 days
Hence, A requires 36 days to complete the work alone.
(ii) C's 1 day work = (A + B + C)'s 1 day work - (A + B)'s 1 day work
=
=
=
Number of days required by C alone = 72 days
Hence, C requires 72 days to complete the work alone.
(iii) (A + C)'s 1 day work =
=
=
No. of days required to complete the work with A and C working together = days
Hence, A and C together will complete the work in 24 days.
Answered By
7 Likes
Related Questions
The price of oranges is ₹ 90 per dozen. Manoj can buy 12 dozen oranges with the money he has. If the price of orange is increased by ₹ 30, how many oranges can Manoj buy?
A and B can do a work in 8 days, B and C in 12 days, and A and C in 16 days. In what time can they do it, all working together?
A and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days.
(i) How long will it take them to do the work, working together?
(ii) In what time can each finish it working alone?
A can do a piece of work in 10 days, B in 12 days and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?