The values of a and b from the table are:
| x | y |
|---|---|
| 3 | 18 |
| 5 | a |
| b | 90 |
| 8 | 48 |
a = 30 and b = 270
a = 30 and b = 15
a = 45 and b = 15
a = 30 and b = 540
Answer
So, we can say that x and y vary directly
Hence, option 2 is the correct option.
In 5 hours, a machine makes 45 screws. In 12 hours, the same machine will make:
36 screws
90 screws
72 screws
108 screws
Answer
Let the machine make x screws.
| Hours | Screws |
|---|---|
| 5 | 45 |
| 12 | x |
Since it is a case of direct variation.
Hence, option 4 is the correct option.
If the cost of 9 pens is ₹ 369, the cost of one dozen pens of the same make will be:
₹ 42
₹ 429
₹ 942
₹ 492
Answer
Let the cost of one dozen pens be x.
| Pens | Cost |
|---|---|
| 9 | 369 |
| 12 | x |
Since it is a case of direct variation.
Hence, option 4 is the correct option.
If y varies directly to x and y = 80 when x = 400; the value of y when x = 25 is:
5
25
75
125
Answer
Let the value of y when x = 25 be a
| x | y |
|---|---|
| 400 | 80 |
| 25 | a |
Since it is a case of direct variation,
Hence, option 1 is the correct option.
A man working 48 hours per week earns ₹ 2,400. If he works for 36 hours per week, he will earn:
₹ 3,200
₹ 900
₹ 1,800
₹ 1,080
Answer
Let the man earn ₹ x.
| Hours | Earing |
|---|---|
| 48 | ₹ 2,400 |
| 36 | ₹ x |
Since it is a case of direct variation.
Hence, option 3 is the correct option.
In the following table, do x and y vary directly:
| x | y |
|---|---|
| 3 | 4.5 |
| 5 | 7.5 |
| 8 | 12 |
| 11 | 16.5 |
Answer
= a constant
Hence, x and y are in direct variation.
In the following table, do x and y vary directly:
| x | y |
|---|---|
| 16 | 32 |
| 30 | 60 |
| 40 | 80 |
| 56 | 84 |
Answer
= not a constant
Hence, x and y are not in direct variation.
In the following table, do x and y vary directly:
| x | y |
|---|---|
| 27 | 81 |
| 45 | 180 |
| 54 | 216 |
| 75 | 225 |
Answer
= not a constant
Hence, x and y are not in direct variation.
If x and y vary directly, find the values of x, y and z :
| x | y |
|---|---|
| 3 | 36 |
| x | 60 |
| y | 96 |
| 10 | z |
Answer
Since a and b vary directly,
Hence, x = 5, y = 8 and z = 120.
A truck consumes 28 litres of diesel for moving through a distance of 448 km. How much distance will it cover in 64 litres of diesel?
Answer
Let the truck consume x litres of diesel.
| Diesel | Distance |
|---|---|
| 28 | 448 |
| 64 | x |
Since it is a case of direct variation.
Hence, the truck will cover 1,024 km distance.
For 100 km, a taxi charges ₹ 1 ,800. How much will it charge for a journey of 120 km ?
Answer
Let the taxi charges ₹ x for 120 km.
| Distance | Charge |
|---|---|
| 100 | ₹ 1,800 |
| 120 | ₹ x |
Since it is a case of direct variation,
Hence, the taxi will charge ₹ 2,160.
If 27 identical articles cost ₹ 1,890, how many articles can be bought for ₹ 1,750 ?
Answer
Let x articles cost ₹ 1,750.
| Articles | Cost |
|---|---|
| 27 | ₹ 1,890 |
| x | ₹ 1,750 |
Since it is a case of direct variation.
Hence, the 25 articles can be bought for ₹ 1,750.
7 kg of rice costs ₹ 1,120. How much rice can be bought for ₹ 3,680?
Answer
Let x kg rice cost ₹ 3,680.
| Quantity | Cost |
|---|---|
| 7 | ₹ 1,120 |
| x | ₹ 3,680 |
Since it is a case of direct variation,
Hence, the 23 kg of rice can be bought for ₹ 3,680.
6 notebooks cost ₹ 156, find the cost of 54 such notebooks.
Answer
Let 54 notebooks cost ₹ x.
| Quantity | Cost |
|---|---|
| 6 | ₹ 156 |
| 54 | ₹ x |
Since it is a case of direct variation,
Hence, the cost of 54 notebooks is ₹ 1,404.
22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day ?
Answer
Let the x men be employed for digging 135 m long trench in one day.
| Men | Length |
|---|---|
| 22 | 27 |
| x | 135 |
Since it is a case of direct variation,
Hence, 110 men should be employed for digging 135 m long trench in one day.
If the total weight of 11 identical articles is 77kg, how many articles of the same type would weigh 224 kg?
Answer
Let x articles weigh 224 kg.
| Articles | Weight |
|---|---|
| 11 | 77 |
| x | 224 |
Since it is a case of direct variation,
Hence, 32 articles would weigh 224 kg.
A train is moving with uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?
Answer
(i) Let x km be distance travel in 36 minutes.
| Distance | Time (in minutes) |
|---|---|
| 120 | 60 (∵ 1 hour = 60 mins) |
| x | 36 |
Since it is a case of direct variation,
Hence, the train will travel a distance of 72 km in 36 minutes.
(ii) Let the train take y minutes to cover 210 km.
| Distance | Time (in minutes) |
|---|---|
| 120 | 60 |
| 210 | y |
Since it is a case of direct variation,
105 minutes = 60 minutes + 45 minutes
= 1 hours 45 minutes
Hence, the train will take 1 hours 45 minutes to cover 210 km.
If a varies inversely to b and b = 12 when a is 8; the value of b when a = 6 is:
72
32
12
16
Answer
Hence, option 4 is the correct option.
12 men can make a certain number of screws in 30 days. The number of screws, of the same type will be made by 24 men in:
15 days
30 days
60 days
none of these
Answer
Let 24 men take x days to make the same number of screws.
| Men | Days |
|---|---|
| 12 | 30 |
| 24 | x |
Since it is a case of inverse variation,
Hence, option 1 is the correct option.
A school has 8 periods in a day, each of 45 minutes duration. Assuming that the number of school hours to be the same and the school has 9 periods in a day, the duration of each period is:
72 minute
180/5 minute
40 minute
60 minute
Answer
Let the duration of each period be x minutes.
| Periods | Duration(in min) |
|---|---|
| 8 | 45 |
| 9 | x |
Since it is a case of inverse variation,
Hence, option 3 is the correct option.
From the given table find the values of a and b:
| x | y |
|---|---|
| 12 | 5 |
| 4 | a |
| 10 | 6 |
| 30 | b |
a = 8 and b = 25
a = 15 and b = 12
a = 12 and b = 90
a = 15 and b = 2
Answer
So, we can say that this is inverse variation.
And, similarly
Hence, option 4 is the correct option.
A hostel has provisions for 200 students for 30 days. If 100 new students join the hostel, the same provisions will last for:
45 days
30 days
60 days
20 days
Answer
Original no. of students in hostel = 200
New no. of students in hostel = 200 + 100 = 300
For 300 students, let the provisions last for x days.
| Students | Provision |
|---|---|
| 200 | 30 |
| 300 | x |
Since it is a case of inverse variation,
Hence, option 4 is the correct option.
Check whether x and y vary inversely or not
| x | y |
|---|---|
| 4 | 6 |
| 3 | 8 |
| 12 | 2 |
| 1 | 24 |
Answer
So,
Hence, x and y vary inversely.
Check whether x and y vary inversely or not
| x | y |
|---|---|
| 30 | 60 |
| 120 | 30 |
| 60 | 30 |
| 24 | 75 |
Answer
So,
Hence, x and y do not vary inversely.
Check whether x and y vary inversely or not
| x | y |
|---|---|
| 10 | 90 |
| 30 | 30 |
| 60 | 20 |
| 10 | 90 |
Answer
So,
Hence, x and y do not vary inversely.
If x and y vary inversely, find the values of l, m and n :
| x | y |
|---|---|
| 4 | 4 |
| 8 | l |
| 2 | m |
| 32 | n |
Answer
Since it is a case of inverse variation,
Hence, l = 2, m = 8 and n = 0.5.
If x and y vary inversely, find the values of l, m and n :
| x | y |
|---|---|
| 24 | l |
| 32 | 12 |
| m | 8 |
| 16 | n |
Answer
Since it is a case of inverse variation,
Hence, l = 16, m = 48 and n = 24.
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
Answer
Let x men do the same work in 42 days.
| Men | Days |
|---|---|
| 36 | 7 |
| x | 42 |
Since it is a case of inverse variation.
Hence, 6 men will do the same work in 42 days.
12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?
Answer
Let 21 pipes take x minutes to fill the tank.
| Pipes | Time (in min) |
|---|---|
| 12 | 42 |
| 21 | x |
Since it is a case of inverse variation,
Hence, 21 pipes will take 24 minutes to fill the tank.
In a fort, 150 men had provisions for 45 days. After 10 days, 25 men left the fort. How long would the food last at the same rate?
Answer
Original no. of men in the fort = 150
New no. of men in the fort = 150 - 25 = 125
For 125 men lets take food will last for x days.
The remaining food would last (45 - 10) = 35 days
| Men | Provision |
|---|---|
| 150 | 35 |
| 125 | x |
Since it is a case of inverse variation,
Hence, the food last for 42 days.
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
Answer
Let 30 men do the same work in x days.
| Men | Days |
|---|---|
| 72 | 25 |
| 30 | x |
Since it is a case of inverse variation,
Hence, 30 men will do the same work in 60 days.
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
Answer
Let x workers do the same work in 70 hours.
| Workers | Time (in hours) |
|---|---|
| 56 | 180 |
| x | 70 |
Since it is a case of inverse variation,
Hence, 144 workers will do the work in 70 hours.
A car takes 6 hours to reach a destination by travelling at the speed of 50 km per hour. How long will it take when the car travels at the speed of 75 km per hour?
Answer
Let the car take x hours at the speed of 75 km per hour.
| Time (in hr) | Speed |
|---|---|
| 6 | 50 |
| x | 75 |
Since it is a case of inverse variation,
Hence, the car takes 4 hours at the speed of 75 km per hour.
A can do a piece of work in 2 days and B can do the same work in 3 days. If A and B work together, the amount of work done by them in 1 day is:
30
1.5
Answer
A's 1 day work =
B's 1 day work =
(A + B)'s 1 day work =
=
=
Hence, option 4 is the correct option.
If of a work can be done in 5 days, the amount of work done in one day will be :
100
4
5
Answer
Let work done in one day be
Work done in 5 days =
Hence, option 1 is the correct option.
Ritu can knit sweater in 4 days and Manish can knit the same sweater in 6 days. If they together knit the same sweater, the number of days taken by them will be:
10 days
5 days
days
days
Answer
Ritu's 1 day work =
Manish's 1 day work =
(Ritu + Manish)'s 1 day work =
=
=
No. days taken by Ritu & Manish together to knit the same sweater =
Hence, option 3 is the correct option.
A and B working together can complete a work in 4 days. If A alone can do the same work in 6 days, then B alone can do the same work in:
12 days
10 days
2 days
24 days
Answer
(A + B)'s 1 day work =
A's 1 day work =
B's 1 day work =
=
=
B alone can do the work in 12 days
Hence, option 1 is the correct option.
A can do a piece of work in 10 days and B in 15 days. How long will they take to finish it working together?
Answer
A's 1 day work =
B's 1 day work =
(A + B)'s 1 day work =
=
=
A and B can do the work in days
Hence, A and B can do the work in 6 days.
A and B together can do a piece of work in days, but B alone can do it in 10 days. How long will A take to do it alone?
Answer
A + B can do the work in days.
(A + B)'s 1 day work =
B's 1 day work =
A's 1 day work =
=
=
A can do the work in days
Hence, A can do the work in 20 days.
A can do a work in 15 days and B in 20 days. If they work together on it for 4 days, what fraction of the work will be left?
Answer
A's 1 day work =
B's 1 day work =
(A + B)'s 1 day work =
=
=
(A + B)'s 4 day work =
=
Remaining work =
=
=
Hence, work wil be left.
A, B and C can do a piece of work in 6 days, 12 days and 24 days respectively. In what time will they altogether do it?
Answer
A's 1 day work =
B's 1 day work =
C's 1 day work =
(A + B + C)'s 1 day work =
=
=
A + B + C can do the work in days
Hence, A + B + C can do the work in days.
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take to mow the field by himself?
Answer
(A + B)'s 1 day work =
(A + B + C)'s 1 day work =
C's 1 day work =
=
=
C can do the work in days
Hence, C can do the work in 168 days.
A can do a piece of work in 24 days, A and B can do it in 16 days and A, B and C in days. In how many days can A and C do it working together?
Answer
A's 1 day work =
(A + B)'s 1 day work =
B's 1 day work = (A + B)'s 1 day work - A's 1 day work
=
=
=
(A + B + C)'s 1 day work =
(A + C)'s 1 day work = (A + B + C)'s 1 day work - B's 1 day work
=
=
=
A + C can do the work in days
Hence, A + C can do the work in days.
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
Answer
A's 1 day work =
B's 1 day work =
(A + B)'s 1 day work =
=
=
(A + B)'s 6 day work =
=
Remaining work =
=
=
No. of days taken by B to finish the remaining work =
=
=
=
=
Hence, B will take days to finish the remaining work.
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
Answer
A's 1 day work =
B's 1 day work =
(A + B)'s 1 day work =
=
=
=
(A + B)'s 2 day work =
=
Remaining work =
=
=
No. of days taken by A to finish the remaining work =
=
=
=
Hence, A will take 10 days to finish the remaining work.
A can do a piece of work in 10 days, B in 18 days, and A, B and C together in 4 days. In what time would C do it alone?
Answer
A's 1 day work =
B's 1 day work =
(A + B + C)'s 1 day work =
C's 1 day work =
=
=
=
=
=
C can do the work in
Hence, C can do the work alone in days.
A can do of a work in 5 days and B can do of the same work in 10 days. Find the number of days in which both working together will complete the work.
Answer
A's 5 days work =
A's 1 day work =
=
B's 10 days work =
B's 1 day work =
=
(A + B)'s 1 day work =
=
=
=
A and B can do the work in days
Hence, A and B working together can complete the work in 12 days.
One tap can fill a cistern in 3 hours and the waste pipe can empty the full cistern in 5 hours. In what time will the empty cistern be full, if the tap and the waste pipe are kept open together?
Answer
Tap's 1 hour work =
Waste tap's 1 hour work =
Both tap's 1 hour work =
=
=
Total time taken by both pipe = hours
Hence, with both taps kept open, the empty cistern will be full in hours.
The value of a when
| x | y |
|---|---|
| 2 | 6 |
| a | 18 |
| 9 | 27 |
is:
1
1.5
9
6
Answer
As
And
So, we can say x and y vary directly
Hence, option 4 is the correct option.
The value of b when
| x | y |
|---|---|
| 3 | 12 |
| b | 9 |
| 12 | 3 |
is:
4
36
24
none of these
Answer
3 x 12 = 36
12 x 3 = 36
So we can say x and y vary inversely
Hence, option 1 is the correct option.
15 note books can be bought for ₹ 240. The number of note books that can be bought for ₹ 160 is:
16
10
18
15
Answer
Let x notebooks cost ₹ 160.
| Quantity | Cost |
|---|---|
| 15 | ₹ 240 |
| x | ₹ 160 |
Since it is a case of direct variation,
Hence, option 2 is the correct option.
6 men can do a certain piece of work in 15 days. The number of men required to complete the same work in 10 days:
30
25
60
9
Answer
Let x men be required to complete the work in 10 days.
| Men | Days |
|---|---|
| 6 | 15 |
| x | 10 |
Since it is a case of inverse variation,
Hence, option 4 is the correct option.
If x is in inverse variation with y and x = 4 when y = 6, the value of x when y = 12 is:
2
18
8
12
Answer
Since it is a case of inverse variation,
Hence, option 1 is the correct option.
Statement 1: Work done varies inversely to the number of persons at work.
Statement 2: Time taken to finish a work varies directly to the number of persons at work.
Which of the following options is correct?
Both the statements are true.
Both the statements are false.
Statement 1 is true, and statement 2 is false.
Statement 1 is false, and statement 2 is true.
Answer
Since, Work done is constant.
Work done increases with more people working. Therefore, work done is directly proportional to the number of persons.
So, statement 1 is false.
Time taken decreases with more people working.
Therefore, time taken is inversely proportional to the number of persons.
So, statement 2 is false.
Hence, option 2 is the correct option.
Assertion (A) : In the following table, p and q are in direct variation.
| p | 3 | 2 | 4 |
|---|---|---|---|
| q | 8 | 12 | 6 |
Reason (R) : If two quantities p and q are in direct variation, then is always constant.
Both A and R are correct, and R is the correct explanation for A.
Both A and R are correct, and R is not the correct explanation for A.
A is true, but R is false.
A is false, but R is true.
Answer
If two numbers p and q are in direct variation, then will be constant.
So, reason is true.
For table,
∴
So, assertion (A) is false.
Hence, option 4 is the correct option.
Assertion (A) : If 3 pipes can fill a tank in 6 hours, then 6 pipes will fill the same tank in half the time.
Reason (R) : Time required to complete a certain work = .
Both A and R are correct, and R is the correct explanation for A.
Both A and R are correct, and R is not the correct explanation for A.
A is true, but R is false.
A is false, but R is true.
Answer
If 3 pipes take 6 hours, then their combined rate of filling the tank is tank/hr.
Each pipe's rate = = tank/hr
Thus, 6 pipes will fill = 6 x tank in an hr.
Time to fill 1 tank by 6 pipes = 3 hours
So, assertion (A) is true.
Time required to complete a certain work = .
This is a standard formula used in time and work problems.
So, reason (R) is true but reason (R) does not clearly explains assertion (A).
Hence, option 2 is the correct option.
Assertion (A) : In the following table, p and q are in inverse variation.
| p | 5 | 2 | 4 |
|---|---|---|---|
| q | 10 | 25 | 12.5 |
Reason (R) : If two quantities p and q are in inverse variation, then is always constant.
Both A and R are correct, and R is the correct explanation for A.
Both A and R are correct, and R is not the correct explanation for A.
A is true, but R is false.
A is false, but R is true.
Answer
We know that,
For two numbers to be in inverse variation,
p x q = constant
So, reason (R) is false.
From table,
So, assertion (A) is true.
Hence, option 3 is the correct option.
Assertion (A) : The cost of 16 bulbs is ₹ 144. The number of bulbs than can be bought for ₹ 270 is 30.
Reason (R) : In inverse variation, the ratio of one kind of like terms is equal to the inverse ratio of the second kind of like terms.
Both A and R are correct, and R is the correct explanation for A.
Both A and R are correct, and R is not the correct explanation for A.
A is true, but R is false.
A is false, but R is true.
Answer
Given,
The cost of 16 bulbs = ₹ 144
The cost of 1 bulb = = ₹ 9
Number of bulbs for ₹ 270 = = 30
So, assertion (A) is true.
In inverse variation,
So, reason (R) is true but, reason (R) does not explains assertion(A).
Hence, option 2 is the correct option.
If x varies directly as y and x = 150 when y = 50. Find:
x, when y = 12.5
y, when x = 75
Answer
- Since it is a case of direct variation,
Hence, when y = 12.5, then x = 37.5.
- Since it is a case of direct variation,
Hence, when x = 75, then y = 25.
If x varies inversely as y and y = 300 when x = 60. Find:
x, when y = 90
y, when x = 300
Answer
1. Since it is a case of inverse variation,
Hence, when y = 90, then x = 200.
2. Since it is a case of inverse variation,
Hence, when x = 300, then y = 60.
Total length of 153 iron bars is 680 m. What will be the total length of 135 similar bars.
Answer
Let x m be total length of 135 bars.
| Iron bars | Length (in m) |
|---|---|
| 153 | 680 |
| 135 | x |
Since it is a case of direct variation,
Hence, 600 m is the total length of 135 bars.
12 men can repair a road is 25 days; how long will 30 men will take to do so?
Answer
Let 30 men take x days to repair the road.
| Men | Days |
|---|---|
| 12 | 25 |
| 30 | x |
Since it is a case of inverse variation,
Hence, 30 men will do the work in 10 days.
The price of oranges is ₹ 90 per dozen. Manoj can buy 12 dozen oranges with the money he has. If the price of orange is increased by ₹ 30, how many oranges can Manoj buy?
Answer
Cost of 1 dozen oranges = ₹ 90
Cost of 12 dozen oranges = ₹ 90 x 12 = ₹ 1,080
Price of oranges is increased by ₹ 30,
∴ New price of 1 dozen oranges = ₹ (90 + 30) = ₹ 120
Let Manoj buy x dozen oranges for ₹ 120 per dozen.
| Oranges (in dozen) | Cost |
|---|---|
| 12 | 90 |
| x | 120 |
As the price of oranges has increased, so now Manoj will be able to buy lesser number of oranges with the money he has.
∴ It is a case of inverse variation.
Hence, Manoj can buy 9 dozen oranges for ₹ 1,080.
A and B can do a work in 8 days, B and C in 12 days, and A and C in 16 days. In what time can they do it, all working together?
Answer
(A + B)'s 1 day work =
(B + C)'s 1 day work =
(C + A)'s 1 day work =
2(A + B + C)'s 1 day work =
=
=
(A + B + C)'s 1 day work =
=
No. of days to complete the work when A, B and C are working together =
Hence, A, B and C working together can complete the work in days.
A and B complete a piece of work in 24 days. B and C do the same work in 36 days, and A, B and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?
Answer
(i) (A + B)'s 1 day work =
(B + C)'s 1 day work =
(A + B + C)'s 1 day work =
A's 1 day work = (A + B + C)'s 1 day work - (B + C)'s 1 day work
=
=
=
Number of days required by A alone = 36 days
Hence, A requires 36 days to complete the work alone.
(ii) C's 1 day work = (A + B + C)'s 1 day work - (A + B)'s 1 day work
=
=
=
Number of days required by C alone = 72 days
Hence, C requires 72 days to complete the work alone.
(iii) (A + C)'s 1 day work =
=
=
No. of days required to complete the work with A and C working together = days
Hence, A and C together will complete the work in 24 days.
A and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days.
(i) How long will it take them to do the work, working together?
(ii) In what time can each finish it working alone?
Answer
(A + B)'s 1 day work =
(B + C)'s 1 day work =
(C + A)'s 1 day work =
2(A + B + C)'s 1 day work =
=
=
=
(A + B + C)'s 1 day work =
=
No. of days required to complete the work when A, B and C are working together = 20 days
Hence, A, B and C working together can complete the work in 20 days.
(ii) A's 1 day work = (A + B + C)'s 1 day work - (B + C)'s 1 day work
=
=
=
∴ A alone will complete the work in 60 days.
B's 1 day work = (A + B + C)'s 1 day work - (C + A)'s 1 day work
=
=
=
∴ B alone will complete the work in 120 days.
C's 1 day work = (A + B + C)'s 1 day work - (A + B)'s 1 day work
=
=
=
∴ C alone will complete the work in 40 days.
A can do a piece of work in 10 days, B in 12 days and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?
Answer
A's 1 day work =
B's 1 day work =
C's 1 day work =
Let the work get completed in x days.
∴ A's 2 days work + B's (x - 3) days work + C's x days work = 1
Hence, the work lasts for 7 days.
Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern may be just filled in 16 minutes.
Answer
Work done by P in 1 minute =
Work done by Q in 1 minute =
Let the first pipe be turned off after x minutes.
Then, P's x minutes work + Q's 16 minutes work = 1
Hence, pipe P must be closed after 12 minutes.